Permits – Office:
Permit B15005268 – Underground Work and Podium/Garage – Issued
Permit W16000521 – Hydrant Meter – Issued
Permit B16000394 – Underground Work – Issued
Permit B16002140 – Johns Creek Bridge – Issued
Permit U16002823 – Johns Creek Bridge Utilities – Issued
Permit U15005273 – Plumbing – Issued
Permit W17000191 – Irrigation Meter – Issued
Permit E16005077 – Electrical – Issued
Permit F16004945 – Fire Alarm – Issued
Office Construction Progress:
Southport Office Construction Site December 25th
Phase 2 construction for Tower 1 has continued this month and is on schedule to be complete and top-out at the roof by early January. Once Tower 1 concrete decks are complete, Tower 2 will pick back up at level 6 and will top out in late April. Vertical pours consisting of concrete shear walls and columns also continue following the decks upward. Miscellaneous curbs fill out the concrete scope for the structure. The slab for Tower 3 is complete.
Level 9 Concrete Deck Pour
Column Rebar Placement
Steel framing operations includes stairs at Tower 1, the exterior soffits, as well as the interior bathroom partitions. Framing and layout for interior rooms is ongoing at the lower levels in both Tower 1 and Tower 2. This includes meeting spaces, offices, and bathrooms along with the lobby areas.
Ductwork Install
At the base of Tower 3, the curtain wall mock-up is complete. The curtain wall exterior support steel continues to be installed in preparation for curtain wall install to begin in mid-January. Curtain wall is currently being delivered to the site to meet this highly anticipated start date.
Mechanical, electrical, plumbing, and fire protection rough-in continues up the towers as shoring is removed. The elevator install for the garage is currently substantially complete with elevator fronts currently being finished throughout the garage levels.
Garage Elevator Fronts