News

News

Construction Update 2017 September

2663_170620_SouthPort_a01_Final

Permits – Office:

Permit B15005268 – Underground Work and Podium/Garage – Issued

Permit W16000521 – Hydrant Meter – Issued

Permit B16000394 – Underground Work – Issued

Permit B16002140 – Johns Creek Bridge – Issued

Permit U16002823 – Johns Creek Bridge Utilities – Issued

Permit U15005273 – Plumbing – Issued

Permit W17000191 – Irrigation Meter – Issued

Permit E16005077 – Electrical – Issued

Permit F16004945 – Fire Alarm – Issued

 

南港办公园区9月22日施工现场

Southport Office Construction Site September 22nd

 

Office Construction Progress:

Valet hotel services continue to use the completed phase 1 garage at the Office for parking.  Recently, a temporary construction tunnel has been completed to allow valet runners to get directly from the Hotel porte cochere to the lower Office garage levels.  This will continue until self-parking can be accommodated in the garage anticipated for late Spring of 2018.

Office - View Down to Hotel Porte Cochere

View Down to Hotel Porte Cochere

The phase 2 Office towers consisting of Tower 1 and Tower 2 continue with elevated concrete deck pours this month.  Current schedule has approximately one deck completed per month for both towers.  By the end of September, both towers will be complete through Level 5 with formwork and MEP rough-in complete at Level 6. Miscellaneous utility work is also being completed as the concrete decks and MEP rough-in continues upward.  In addition, construction for the garage elevators from level P1 – level P3 continues this month with shaft wall and equipment install.

Office - Elevator Shearwalls

Elevator Shearwalls

Precast concrete is being installed on the west side of tower 2 along with final sealing of the concrete precast at the upper parking levels.  The slab on grade for the remainder of the ground level parking at tower 3 that ties into the east side of tower 2 will also be completed by early October.  The general contractor is now using the road that was backfilled along the main Bristol drive for truck staging and better site access.

Office - Tower 3 Slab on Grade

Tower 3 Slab on Grade