Permits – Office:
Permit B15005268 – Underground Work and Podium/Garage – Issued
Permit W16000521 – Hydrant Meter – Issued
Permit B16000394 – Underground Work – Issued
Permit B16002140 – Johns Creek Bridge – Issued
Permit U16002823 – Johns Creek Bridge Utilities – Issued
Permit U15005273 – Plumbing – Issued
Permit W17000191 – Irrigation Meter – Issued
Permit E16005077 – Electrical – Issued
Permit F16004945 – Fire Alarm – Issued
Office Construction Progress:
Southport Office Construction Site February 22nd
Phase 2 construction is on schedule as Tower 1 has been topped out! All concrete decks have been poured to the roof as the concrete contractor has jumped back over to Level 7 to continue with the elevated decks for Tower 2. Decks will continue up for Tower 2 with topping out planned for late April. The steel structure for the mechanical screen is being installed at the Tower 1 roof. In addition to the elevated decks, CMU concrete walls are being finished at the interface between the parking and occupiable office spaces throughout the garage. The slab for Tower 3 is complete.
Roof Deck North
Tower 1 CMU wall between Garage and Office
Framing and layout for interior rooms including meeting spaces, offices, and bathrooms is ongoing at the lower levels in both Tower 1 and Tower 2. Ceiling framing will continue next to fit out the common spaces with wall board to follow as mechanical systems rough-in, electrical, plumbing, and fire protection is completed for each floor.
Tower 1 Bathroom Framing
Elevator install for the parking levels is nearly complete. This includes finishing of the elevator vestibules, cabs, and elevator surrounds with all final finishes and associated equipment including call buttons, lanterns, and intercoms. As the garage elevators are completed, the contractor will move over to begin install on the tower elevators as the support steel for the tower elevators is ongoing.
Main Lobby Elevators
The curtain wall glazing at the exterior of Tower 1 has begun! This will continue counter-clockwise around and up the building at Tower 1 with an anticipated completion for the Tower 1 exterior at the end of March. The curtain wall is stocked up to level 8 to facilitate this schedule and will continue to be delivered to the site as the reshores are removed and upper floors are more accessible. In addition, support steel for the exterior stone and mounting clips for the curtain wall continues to be installed going up Tower 1 to get ahead of the curtain wall. Stone install that frames the lower levels of the curtain wall system will begin in March as well.
Tower 1 Curtain Wall Install
In addition to the curtain wall install, storefront frames, waterproofing, and subsequent glazing has also begun at the ground level retail for both Tower 1 and Tower 2.
Tower 1 Storefront