News

News

Construction Update 2018 July

2663.03_180202_Southport_a01_Updates

Permits – Office:

Permit B15005268 – Underground Work and Podium/Garage – Issued

Permit W16000521 – Hydrant Meter – Issued

Permit B16000394 – Underground Work – Issued

Permit B16002140 – Johns Creek Bridge – Issued

Permit U16002823 – Johns Creek Bridge Utilities – Issued

Permit U15005273 – Plumbing – Issued

Permit W17000191 – Irrigation Meter – Issued

Permit E16005077 – Electrical – Issued

Permit F16004945 – Fire Alarm – Issued

 

照片 2018-7-23 下午1 19 26

Southport Office Construction Site 07/23/2018

Tower 1 construction continues this month with an emphasis on the Living Room lobby preparation so that finishes can be installed at the public amenity levels. The skylight has been installed at this entry which will be a great show piece for the lobby and allow an abundance of natural light into the space.

rsz_img_9975

rsz_img_9968

Tower 1 Living Room Lobby – Skylight

 

The exterior soffit at Level 1 is ongoing with the drywall complete and plaster finish to follow. Sheetrock work in the tower is ongoing and is complete up to level 9. Floor tile in the bathrooms is up to level 5. The interior elevator finishes are nearly complete and the ceilings at the elevator lobbies are framed up to level 6. At the roof, the mechanical equipment install is ongoing while the metal panel screen wall will be complete by the end of the month.

rsz_img_9960

Tower 1 – Bathroom Tile Install

 

Tower 2 construction is catching up to Tower 1 as both towers are on schedule to be complete by December of 2018. Framing in the tower is complete to level 9 along with ceiling framing complete to level 8. Sheetrock work is ongoing and is complete up to level 6. Mechanical, electrical, plumbing rough-in is ongoing up the tower ahead of sheetrock cover. At the roof, roof insulation and waterproofing are currently being installed. The stone work at the exterior façade is complete on the North and West facades. Handrails, pavers, and metal panel are all in process at the level 4 outdoor terrace.

rsz_img_0031

Tower 2 – North Facade

rsz_1img_0013

Tower 2 – West Façade

 

Tower 3 concrete decks are on schedule to be completed by the end of 2018 as they are currently up to level P5/Office level 3. Site preparation has been ongoing for the plaza area between towers 1 and 2. The waterproofing is complete with foam build-up, soil, and hardscape to follow.

照片 2018-7-23 上午11 17 16

Tower 3 – Level 3 Concrete Deck

rsz_tower_3_-_level_3_deck_prep

Tower 3 – Level 3 Deck Prep

 

The garage continues to be used for Hyatt guests and retail patrons for self-parking. The storefront doors for the elevator lobbies are currently being installed while wayfinding signage that supports Tower 1 and Tower 2 will be complete in the garage by the end of the month.

rsz_img_0037

IMG_0042

Parking Garage – Signage

 

window 4X3 072018 resized for website