News

News

Construction Update 2018 June

In recognition of Southport’s contribution to local job creation and economic development, City of Renton has renamed the road from I-405 to Southport as Southport Dr N.

照片 2018-6-4 上午10 28 45_meitu_1

照片 2018-6-12 下午7 36 16

Southport Dr N Sign

 

Office Construction Progress:

2663.03_180202_Southport_a01_Updates

Permits – Office:

Permit B15005268 – Underground Work and Podium/Garage – Issued

Permit W16000521 – Hydrant Meter – Issued

Permit B16000394 – Underground Work – Issued

Permit B16002140 – Johns Creek Bridge – Issued

Permit U16002823 – Johns Creek Bridge Utilities – Issued

Permit U15005273 – Plumbing – Issued

Permit W17000191 – Irrigation Meter – Issued

Permit E16005077 – Electrical – Issued

Permit F16004945 – Fire Alarm – Issued

 

照片 2018-6-25 下午4 49 58

Southport Office Construction Site 06/25/2018

Tower 1 construction continues this month with predominantly interiors and roof work. At the roof, the mechanical equipment is being installed, balanced, and tested. The perforated metal panel screen wall will start install by the end of the month. The exterior stone looks great at the lower levels as complimentary interior stonework at the building main entry will be complete by the end of the month.

Tower 1 - Rooftop Mechanical Units

Tower 1 – Rooftop Mechanical Screen

The structural glass wall at the main lobby has been installed which will allow the main lobby to get dried in and finishes to commence. Sheetrock work in the tower is ongoing and is complete up to level 5. Floor tile will begin later this month as well. Mechanical, electrical, and plumbing rough-in is ongoing up the tower and approved for sheetrock cover up to level 7. The interior elevator finishes are ongoing as well.

照片 1980-1-1 上午12 02 32

IMG_9908

Lobby – Structural Glass Wall

Tower 2 curtain wall was completed this past week! Storefront windows at the lower level retail are complete as the entry vestibule framing and preparation for site work continues this month. Framing in the tower is complete to level 9 along with ceiling framing complete to level 7. Sheetrock work will begin at level 3 by the end of June. Mechanical, electrical, plumbing rough-in is ongoing up the tower. The tower elevators have begun install while the level 3 terrace skylight is on schedule to be installed by the beginning of July.

IMG_9921

照片 1980-1-1 上午12 02 25

Tower 2 – Curtain Wall Completed

Site preparation has been ongoing for the plaza area between towers 1 and 2.  Site preparation includes waterproofing, planter construction, irrigation/lighting rough-in, and hardscape.

IMG_9905

IMG_9911

Plaza Waterproofing

Tower 3 concrete decks are currently up to level P3/Office level 2 and will continue through the end of 2018. The garage is operational for six levels of self-parking.  Hyatt guests and employees are currently using the garage.

IMG_9927

      Tower 3 – Concrete Floors in Foreground

IMG_9897

Tower 3 - P3 Deck Pour

Tower 3 – P3 Deck Pour